A Saudi Fund for Development (SFD)-funded livelihood restoration project in Balochistan aims to improve water access for rural and livestock-dependent communities through the construction of 30 community livestock ponds, 40 water tanks and 10 water diversion structures.

According to project information reported by the Associated Press of Pakistan (APP), the grant-funded initiative is being implemented through the Project Management Unit of the Human Rights Affairs Department in Balochistan. The project has an estimated cost of $1.50 million and also includes well boring and drilling, along with livelihood support activities.

Project documents cited in reporting indicated that approximately $0.48 million had been spent and physical progress stood at 32% as of the latest available reporting around October 2026.

The livestock ponds are intended to improve water availability for communities that depend on livestock for their livelihoods. The project also includes 40 water tanks and 10 water diversion structures, alongside the boring and drilling of wells.

Procurement was at different stages across the project components. Bidding for excavation of the livestock ponds had begun in 2024, with bid evaluation awaiting approval from the SFD. The bidding process for water tanks was also underway.

For the water diversion structures and related works, the SFD had approved the bid evaluation, while approval of the draft agreement remained pending, according to the reported project documents.

The initiative also includes livelihood support, such as the provision of sewing machines to help community members develop income-generating activities.

An earlier component involving the construction of 150 rooms was removed during a review of the project scope. The change was reported to have generated estimated savings of $0.13 million.

An SFD mission visited in February 2026 to review implementation progress. Several bid evaluations had been submitted for the fund’s concurrence, according to the available reporting.