Balochistan has set completion targets between 2026 and 2028 for 10 major highway projects with a combined approved cost of Rs644.6 billion, aiming to improve road connectivity, strengthen trade routes and upgrade transport infrastructure across the province.
According to official documents available to Wealth Pakistan, the projects are being implemented under the Public Sector Development Programme (PSDP). Three projects are scheduled for completion by December 2026, six have deadlines in 2027, and one major highway project is targeted for completion in June 2028.
The projects cover key sections of national highways N-25, M-8 and N-50, connecting major urban centres and remote districts while supporting access to commercial routes and regional transport networks.
N-25 Receives Major Investment
A significant share of the investment is concentrated on National Highway N-25, a key route linking Karachi, Quetta and Chaman. Several sections are being upgraded or widened to improve transport capacity along this important corridor.
The 330.52-kilometre Khuzdar–Kuchlak section has an approved cost of Rs98.90 billion. According to the documents, 61 per cent of construction had been completed, with Rs42.86 billion spent by September 2026. The project is scheduled for completion in December 2027.
Another major project covers the 273-kilometre Karachi–Kararo and Wadh–Khuzdar sections, with an approved cost of Rs183.42 billion. Construction progress stood at 19 per cent, while expenditure had reached Rs36.53 billion. Its completion deadline is December 2027.
The 187-kilometre Kararo–Wadh and Kuchlak–Chaman section has an approved cost of Rs132.75 billion. The project had recorded 22 per cent construction progress, with Rs30.07 billion spent. It is also scheduled for completion in December 2027.
Meanwhile, the 22.7-kilometre Quetta Western Bypass widening project on N-25 is nearing completion. With an approved cost of Rs6.89 billion, the project had achieved 85 per cent construction progress, while expenditure reached Rs6.05 billion. Completion is targeted for November 2026.
Road Projects Targeted for Completion in 2026
Three projects are scheduled for completion by the end of 2026, including the Quetta Western Bypass, the Nokundi–Mashkel road and the Jhal Jhao–Bela road.
The 103-kilometre Nokundi–Mashkel road project has an approved cost of Rs7.71 billion. Construction progress had reached 79 per cent, while expenditure stood at Rs6.94 billion. Completion is expected in December 2026.
The 79.89-kilometre Jhal Jhao–Bela road project, with an approved cost of Rs16.22 billion, had achieved 70 per cent progress. Expenditure had reached Rs13.87 billion, with completion also scheduled for December 2026.
These projects are intended to improve road access in areas where transport links are important for local movement, trade and access to services.
M-8 and N-50 Projects to Improve Regional Connectivity
Work is also progressing on sections of the M-8 and N-50 highways, which form part of the province’s wider road network.
The 168-kilometre Awaran–Nal section of the M-8 has an approved cost of Rs32.24 billion. Construction progress stood at 52 per cent, with Rs20.45 billion spent. The project is scheduled for completion in June 2027.
The 146-kilometre Hoshab–Awaran road project, with an approved cost of Rs25.84 billion, had reached 64 per cent completion. Expenditure stood at Rs9.75 billion, and the deadline is June 2027.
On N-50, the project to widen and improve the Yarik–Sagu–Zhob section, including the Zhob Bypass, has an approved cost of Rs76.49 billion. However, construction progress remained at 2 per cent, with expenditure reported at Rs975 million. Completion is targeted for November 2027.
The 305-kilometre Kuchlak–Zhob section of N-50 is the major project scheduled for completion in 2028. It has an approved cost of Rs63.60 billion, with construction progress at 16 per cent. Expenditure had reached Rs11.71 billion by September 2026, and completion is scheduled for June 2028.